Mixed Insurance Banners Health Insurance for Visitors to USA

Announcement

Collapse
No announcement yet.

PERM processing time

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • Originally posted by Virgo11 View Post
    EB3 Applied in December 2009, got a Audit in May 2010. Query was replied in June 2010 first week. Approved May 1st 2011.

    EB2 Applied in April 2011 first week and still in processing.
    EB2 got approved in 2 months. Approved on Jun 14th 2011

    Comment


    • EB2 approved from CA

      Applied Aug 22 and got it approved on Nov 16.

      Comment


      • Perm/LC/9089 not being filed

        Perm/LC/9089 not being filed

        My Attorney is asking for the below confirmation without which they cant file.

        For me in January my 6th year will start and technically they are saying they cant file after 31st Jan 2012.

        This is what they need.

        "We still need confirmation from the local HR that there have been no layoffs in your position or a similar role in the geographic area within the past 6 months. Once we receive confirmation, we will file the application with the Dept. of Labor. ".

        My Manager has responded back saying that there has not been any layoffs in his deptt however they want to get the confirmation from HR as well. And if HR says yes there have been layoffs then they are asking for separate questionaire to be sent to them statung the reasons for the individuals layoff and why that person was a misfit. Is it REALLY THAT DIFFICULT!!

        Any help would be highly appreciated.

        Comment


        • View current processing time - DOL website

          You can see the current application processing times at http://icert.doleta.gov (under 'Perm Processing Times' tab).

          My status: EB2 - filed Oct 5, 2011 - Jan 10, 2011 not approved yet.
          Last edited by mohnish82; 01-10-2012, 11:45 AM. Reason: including my status

          Comment


          • current processing time

            mohnish82 pls. update once you get your approval, also, if others can update it will be helpful for us..

            Comment


            • Nov 2011 approvals?

              Hi,
              did anyone receive PERM approval for PD in Nov 2011?
              plz post

              Comment


              • latest PERM factsheet as of 2/15/2012

                this is ridiculous but DOL has released the PERM factsheet as of 2/15/2012 and they are still reviewing October 2011 cases.the denial rate has gone up to 20% and approval rate is about 74.5 %. Also looks like they are focusing more on audit and appeal cases then standard cases.

                Comment


                • LC Applied in Dec 2011

                  My company has filed for LC with PERM in Dec 2011 - EB3.

                  My 6 year term for H1B will be done in Sep 2012.

                  What are the chances I will get approval in time so that I can file I-140 (premium) and have H1B extended?

                  Help me with any information or views.

                  Thanks,
                  Prasad

                  Comment


                  • just saw a Dec 1st '11 approval

                    plz update if anyone has got any recent Nov/Dec '11 approvals.

                    Comment


                    • PERM fact sheet as of 3/5/12

                      DOL has released the latest fact sheet as of 3/5/12,

                      as per that,

                      case processed: 21420

                      certified:13640 (64%)
                      denied: 3450 (16%)
                      withdrwan: 1080 (5%)

                      not sure what other missing 15% is.

                      Comment